The new spray park will be located in the northwest corner of Pioneer Park. A scheduled opening for July 4 has been delayed until Memorial Day weekend in 2015. Construction will start this fall.

CITY OF PUYALLUP — Courtesy photo

The spray pad, scheduled to open July 4 in Pioneer Park, will now not open until Memorial Day weekend in 2015 at the earliest.

Fife-based Nordic Construction came in as the only bidder on the project. The firm's bid, however, was 20 percent more than the budgeted amount for the project.

On April 8, the Puyallup City Council unanimously voted to reject the bid because it was non-competitive.

Sarah Harris, parks and recreation administrator, said the city wants to present the best product possible at the best price.

The city will solicit for new bids in late May or early June. Construction on the splash pad will begin in mid-September.

Read the April 23 print edition of the Herald for the full story.

Andrew Fickes: 253-552-7001

andrew.fickes@puyallupherald.com

Twitter: @herald_andrew

The Puyallup Herald is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Commenting FAQs | Terms of Service